Most home projects start with the same question: do I need to apply to the council, or can I just build? That is really a question about planning permission versus permitted development. The two are closely linked, but they work in different ways, take different amounts of time and suit different projects. This guide explains each route in plain terms, for homes in England, so you can see which one your project is likely to follow.
Planning permission versus permitted development: the short answer
Planning permission is consent from your local council for a specific proposal. You send in an application with drawings, the council looks at it, and it grants or refuses permission.
Permitted development is a planning permission that already exists. The government has granted it nationally, for certain kinds of work, so you don't need to apply to the council for it. It comes from a piece of law called the Town and Country Planning (General Permitted Development) (England) Order 2015.
So permitted development is not a way of building "without permission". It is permission given in advance, with strict limits and conditions attached. If your project stays inside every limit, you can use it. If it breaks even one, you need to apply for planning permission instead.
How permitted development works
Permitted development rights are set out in classes. Each class covers one kind of work, such as extending a house, altering a roof or putting up an outbuilding. Each has its own list of limits on size, height and position, and conditions on things like materials.
For a house, some of the main limits on extensions are:
- A single-storey rear extension can go up to 3 metres beyond the original rear wall, or 4 metres on a detached house.
- A single-storey extension can be no more than 4 metres high.
- If any part of the extension is within 2 metres of the boundary, the eaves can be no higher than 3 metres.
- A side extension must be single storey and no wider than half the width of the original house.
- An extension of more than one storey must be at least 7 metres from the boundary opposite the rear wall.
- Extensions and other buildings must not cover more than half the land around the original house.
- The outside must be of a similar appearance to the existing house.
Loft conversions have their own limits. The extra roof space can be up to 40 cubic metres on a terraced house and up to 50 cubic metres on other houses, and any earlier roof extension counts towards that figure.
These are only the headline rules. The full conditions are in the government's technical guidance for householders, and every one of them has to be met. Our guide on how far you can extend without planning permission goes through the extension sizes in more detail.
When permitted development is not available
Not every home has these rights, and some have fewer of them.
- Flats and maisonettes. The householder rights for extensions, lofts and outbuildings apply to houses. They do not apply to flats or maisonettes.
- Designated areas. Rights are more limited in conservation areas, National Parks, Areas of Outstanding Natural Beauty, World Heritage Sites and the Broads. In these places, side extensions, rear extensions of more than one storey, roof extensions and some types of cladding are not permitted development.
- Article 4 directions. A council can remove particular rights in an area by making an Article 4 direction. These are most common in conservation areas.
- Planning conditions. A council can remove rights through a condition on an earlier planning permission. This is worth checking on newer houses and estates.
- Homes created through permitted development. A house or flat that was itself created using permitted development rights, such as a converted building, usually can't use the householder rights for later work.
- Listed buildings. Different requirements apply to listed buildings, so always speak to the council before planning any work to one.
If any of these apply to you, the answer is not always "no". It means the work needs a planning application, so the council can look at it properly.
How a planning application works
When permitted development doesn't cover your project, you apply to the council for planning permission. The application includes drawings of the house as it is now and as you want it to be, together with forms and a fee.
The council must decide an application in line with its development plan, unless other relevant planning matters point the other way. These are called material considerations. They are about the planning effects of a proposal. Purely private interests, such as the effect on the value of a neighbouring property, are generally not material.
The time limit for a decision on most applications is 8 weeks. Larger and more complex schemes have longer limits. If the council doesn't decide a valid application in time, and you haven't agreed an extension, you have a right to appeal.
The main difference from permitted development is that a planning application is a judgement, not a checklist. The council weighs your design against its policies. That brings some uncertainty, but it also brings freedom. You are not tied to the fixed sizes in the permitted development rules, so a well-argued design can go further than those rules allow.
The middle route: prior approval
Some permitted development rights come with an extra step called prior approval. You still don't need full planning permission, but you must ask the council to approve certain specified points before work starts. The council can only consider those points, and nothing else.
The best-known example for homeowners is the larger single-storey rear extension. A house can extend up to 6 metres at the rear, or 8 metres if it is detached, but only through the neighbour consultation scheme. The council tells the adjoining neighbours about the plans. If a neighbour objects, the council decides whether the effect on them is acceptable. This larger size is not available in conservation areas and the other designated areas listed above.
Which route suits your project?
There is no single best route. It depends on the house and on what you want to build.
Permitted development tends to suit you when:
- your home is a house with its rights intact;
- the design fits comfortably inside every limit;
- you want as much certainty as possible before spending money on detailed drawings.
A planning application tends to suit you when:
- you live in a flat or maisonette, or your rights have been removed or limited;
- the space you need is bigger, taller or in a different position than the limits allow;
- you would rather have the design that works best for the house than one shaped by the limits.
It is common to compare both early on. A design that is trimmed to squeeze inside permitted development is not always the better home. Equally, there is little point in applying for planning permission for something you already have permission to build.
Proving that work is permitted development
With permitted development, nobody at the council signs anything off unless you ask them to. That is where a lawful development certificate comes in.
A lawful development certificate is a legally binding decision from the council that your proposal is lawful. It is optional. You apply with drawings and an explanation of why the work falls within the rules, and the fee for a proposed development is half the normal planning fee.
Many homeowners choose to get one. It settles any doubt before building starts, and it gives you a document to show a buyer or their solicitor when you come to sell. It is not a replacement for planning permission: if the work falls outside the rules, you still need to apply.
We prepare the drawings and applications for both routes. You can read more about our permitted development service, including lawful development certificates.
Building Regulations apply either way
Planning and Building Regulations are separate. Permitted development rights do not override the need to comply with other consents, and nor does a planning permission. Whichever planning route you use, the building work itself will normally need Building Regulations approval too. Planning looks at whether the proposal is acceptable. Building Regulations look at how it is built.
Common questions
Is permitted development the same as not needing planning permission?
Not quite. Permitted development is a planning permission that the government has already granted nationally. You don't need to apply to the council for it, but you must stay within all of its limits and conditions.
Do internal changes need planning permission?
Planning permission is only needed for work that counts as "development" in law. Works to the inside of a building, such as interior alterations, are not treated as development, so they don't need planning permission. Listed buildings are different, and Building Regulations may still apply.
Can the council take away permitted development rights?
Yes. A council can remove rights in an area with an Article 4 direction, or through a condition on a planning permission. An Article 4 direction can't be used to stop work that has already started or been finished.
Do I have to get a lawful development certificate?
No, it is optional. It is the only way to get a legally binding decision from the council that your project is permitted development, which is why many homeowners apply for one before they build.